Webthe nature of the work to be performed, the Contractor shall state this exception and provide a justification. (1) The Contractor shall identify each major phase of work that will be performed on this contract. Within each major phase, all activities, tasks or Definable Features of Work (DFOWs) shall be identified that will require an AHA. WebAccording to theUSACE Best Practice, Definable Features of Work in a project are each individual task of a project that must be sufficiently broken down for the QC process. To …
NAVFAC — PreConstruction Plans
WebIf you’re not already familiar with the term, a Definable Feature of Work (DFOW) is what you might think of as a construction task. The Corps of Engineers describes a DFOW as a task that is separate and distinct from … WebJun 23, 2005 · List of Definable Features of Work (DFOW) including list of design submittal packaging. DFOW is a task that is separate and distinct from other tasks and has control requirements and work crews unique to the task. For the CQC Plan, a plan to implement the "Three Phases of Control" for each DFOW. bkk phoenix fusion
Module 1: INTRODUCTION Submodule 1: What is …
WebA list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and is … WebThe project tasks for this CTO are grouped into definable features of work, which are work activities that are significant enough to warrant distinct plans and specifications. The definable features of work for this project are: • Mobilization and Site Preparation. • Treatment Well and Monitoring Well Installation. • Field Piping/Trenching. WebJul 31, 2013 · revised and amended as necessary throughout the project. For example, a basic list of definable features of work (DFOWs) has been included. This list will become more detailed as the work progresses. All modifications to the CQCP will be approved by the CPG before implementation. 1.1 Project Background bkkprep firefly login